Guest

Preview Tool

Cisco Bug: CSCum33615 - Group Calendar not forecasting in job unless recalculated

Last Modified

Jan 26, 2017

Products (22)

  • Cisco Workload Automation
  • Cisco Tidal Enterprise Adapter for Oracle E-Business Suite
  • Cisco Tidal Enterprise Adapter for Oracle Database
  • Cisco Tidal Enterprise Adapter for Web Services
  • Cisco Tidal Enterprise Scheduler 6.2
  • Cisco Tidal Enterprise Adapter for SAS
  • Cisco Tidal Enterprise Adapter for VMware
  • Cisco Tidal Enterprise Adapter for Informatica
  • Cisco Tidal Enterprise Adapter for SAP
  • Cisco Tidal Enterprise Adapter for Cognos
View all products in Bug Search Tool Login Required

Known Affected Releases

5.3.1 6.1.0 6.2.1

Description (partial)

Symptom:
In job definition, assigning a job to a new Group Calendar, there is no forecast.

We also see the job definition forecast missing dates when using group calendars that use list calendars that were modified. The group calendar is correct but the job never syncs to the calendar. We also notice that when you recalculate calendars (calculate all calendars), the group that contains the list calendar does not compile. It has to be calculated explicitly to sync the job forecast and get it compiled correctly, else job will not be in schedule for added date(s).

Conditions:
1. In job definition, assigning a job to a new Group Calendar, there is no forecast. 
Repro:
Create group calendar includes a list (includes today) and All Saints Day. Create job to use calendar.  click forecast and its blank. When you save chose "today" as effective date.  Today's date is a selection, but it was not bold. It did run.  Went back to look at job def and the forecast.  It was not showing any dates.

2. We also see the job definition forecast missing dates in group calendars that use list calendars that were modified. Group calendar is correct but the job never syncs to calendar. Also notice that when you recalculate calendars (calculate all calendars), the group that contains the list calendar does not calculate. Must be calculated explicitly to sync to job so it schedules correctly.

Repro:
1. Create list calendar with 1 date
2. Create group calendar with list calendar and Weekend calendar
3. Create a job, use group calendar
4. Check group, it is correct. Check job forecast on definition and it looks good
5. Add a new date to list calendar.
6. Check group forecast, it looks good.
7. Check job forecast, it is missing new date! 
8. Recalculate Calendars 
9. not all calendars recalculate so the job was still not forecasted correctly. job will not be compiled into schedule. Create the schedule for the date that you added in step 5 and see job missing.
10. Recalculate just the group calendar explicitly.
11. Check job's forecast its good.
Bug details contain sensitive information and therefore require a Cisco.com account to be viewed.

Bug Details Include

  • Full Description (including symptoms, conditions and workarounds)
  • Status
  • Severity
  • Known Fixed Releases
  • Related Community Discussions
  • Number of Related Support Cases
Bug information is viewable for customers and partners who have a service contract. Registered users can view up to 200 bugs per month without a service contract.